Location
Beveren
Client
Oiltanking Antwerp – Gas Terminal
Start of the construction
06/2020
End of the construction
12/2020

OT AGT Package 8

The project involves the construction of a process zone belonging to tank T.04 (Eucalyptus project), consisting of foundations, earthworks and underground pipes. 

The works consist of carrying out pile foundations, consisting of 246 soil displacement screw piles diameter 36cm / diameter 41cm.

In addition, earthwork, formwork, reinforcement and concreting of foundation slabs (T.04 Piperack, compressor area, condenser area, booster pump area, manifold area, fire walls, T.02 Piperack and sleepers, propylene cooling unit, DW GW SO. Heaters area and propylene cooling unit), including the pouring of associated anchors for third parties (equipment, steel structure, ...)