Noise barriers Borgerhout

Location
E313 Borgerhout
Client
Agentschap Wegen en Verkeer Antwerpen
Start of the construction
06/2020
End of the construction
08/2020

Demolition and installation noise barriers

This project involved the demolition of concrete noise barriers (+/- 1,500 m2) over a stretch of about 640 m along the E313 motorway. In addition, the right-hand lane (next to the rush-hour lane) was milled down 8 cm over the same stretch. We also broke up some concrete embankment gutters.

After the demolition work, we installed new acoustic panels and provided the road surface with a new layer of asphalt.