Location
Anderlecht, Line 28
Client
Infrabel
Start of the construction
10/2020
End of the construction
08/2021

Renewal of bridge decks line 28

For this project, we carried out the renewal of two underpasses during a limited outage of six days. The waterproofing of the vaulted deck of the old Kuregem station was also renewed. The waste produced by the works was disposed of separately. This included the old steel bridges and the concrete elements. Given the decommissioning of the tracks, we had to replace the bridges within a very tight timing. This required faultless and extensive preparation.