ECODUCT Hoeilaart

Ligging
Brussels ring (RO) at the level of the Zoniënwoud Forest in Hoeilaart
Opdrachtgever
Flemish Government, Agency for Roads and Traffic Flemish Brabant
Start der werken
03/2016
Einde der werken
03/2018

Ecoduct Hoeilaart

Between 2016 and 2019 we built an ecoduct over the Brussels ring road (RO), and this at the level of the Zoniënwoud Forest in Hoeilaart. In addition to the technical aspect, great importance was also attached to the architectural character, the ecological and sustainable aspect. This increased the complexity of the implementation.

Landscaping

100.000 cubic meters

Foundation

112 foundation piles

diameter of 1 meter

depth of 16.7 meters




 

Bridge deck

58 precast beams

dimensions of 25 meters

weight of 40 tons