Start of the construction
05/2025
End of the construction
05/2026
Reconfiguration of the R32 intersection and construction of a new cycle tunnel
In Hooglede, together with our colleagues from Stadsbader, we are reconfiguring the R32 intersection. We are responsible for the construction of a new cycle tunnel. In an excavation secured with temporary sheet piles, we build the tunnel and the pump chamber. The structure is then completed up to ground level, after which the temporary sheet piles are removed.