Arcelor Castfloor

Location
Gent
Client
Arcelor Mittal Gent
Start of the construction
07/2020
End of the construction
04/2021

Repair of blast furnace B

During a shutdown, we repaired blast furnace B. In that context, we realised the demolition, repair and modification of work floor, casting floors and support structures. This included dismantling plate beams, demolishing overhead walls on the casting floors, modifying drill foundations and building a new insertion, concreting new beams and constructing and installing precast beams, including repairing the walls that had been broken away.